HomeCase Study
    Industrial Automation & SCADA · Mining

    Two coal lines, 0 minutes of downtime during the rebuild

    RMU Kakanj replaced 14-year-old control electronics and analog supervision at its Vrtlište coal handling plant with an independent, dual-line SCADA system — installed without stopping production once.

    Client
    RMU "Kakanj" — Pogon Vrtlište
    Location
    Kakanj, Bosnia & Herzegovina
    Sector
    Coal mining · process handling
    Delivered with
    Spark Industry d.o.o. Zenica
    2
    Independent technological lines — now fully decoupled
    14 yrs
    Age of the original control & supervision system
    10 yr
    Rated service life the old electrical equipment had exceeded
    0 min
    Unplanned production stoppages during the changeover
    ~16
    Machines monitored live, per line, on the new SCADA

    An hour of downtime at this plant costs roughly 25,000 BAM (~€12,500) — which is what makes these zero minutes during the changeover a real saving, not just a statistic.

    The Challenge

    A 14-year-old nervous system running two lines that couldn't fail independently

    Vrtlište is where RMU Kakanj's coal becomes a shipment. Technological Line 1 receives and processes raw coal and stacks it onto an elevated storage pile; Technological Line 2 reclaims coal from that pile and loads it into rail wagons bound for Termoelektrana Kakanj, the thermal power plant next door. Long overland conveyor bridges — the steel gantries that define the site's skyline — carry material between every stage.

    The transfer and handling system had been running for 14 years, and its electrical equipment had already outlived its rated 10-year service life. Reliability was degrading the way aging industrial electronics do: intermittent faults, slow manual diagnosis, and — the real risk — no separation between the two lines. A fault on one could take down the other, coupling risk across the whole plant instead of containing it.

    Overhead view looking up the elevated conveyor bridge structure at the RMU Kakanj Vrtlište coal handling plant
    The Solution

    Rebuilding control, motor starting, and supervision — line by line, without stopping either one

    Comex worked alongside Spark Industry d.o.o. Zenica and RMU Kakanj's own Electrical Services Department to replace the plant's control cabinets, motor starting, and operator supervision from the field level up.

    New Schneider Electric Modicon M241 PLC control cabinet, fully assembled and pre-wired before installation
    Control hardware

    A Schneider Electric Modicon M241 PLC now sits at the core of each cabinet, backed by a Schneider XPS-MC safety relay for machine safety functions, DIN-rail motor protection breakers, and a managed network switch for the supervision layer above it.

    Motor starting

    Every drive on site — chain conveyors, the screen, the picking table, the crusher, both main conveyors, the reduction conveyor, the mill — now starts through variable frequency drives, with one soft-starter covering the remaining load, in place of direct-on-line starting.

    Why it matters

    Controlled acceleration cuts mechanical shock loading on gearboxes and belts, gives operators real speed control instead of on/off, extends motor and switchgear life, and uses meaningfully less energy than DOL starting did.

    Independence by design

    The most consequential change is structural, not visual: Line 1 and Line 2 are now fully independent, electrically and logically. A fault on the reclaim/loading side has no path to the processing/stacking side, or back the other way — removing the plant's single biggest source of unplanned, cascading downtime.

    Zero-downtime cutover

    Cabinets arrived fully assembled, pre-programmed and pre-tested. Installation was confined to non-operating windows, so the swap itself never required stopping production.

    Schneider Electric Altivar variable frequency drives installed in the new motor control panel
    Supervision & Visualization

    One screen per line, live status on every machine

    Dispatchers and the electrical maintenance team now get a real-time, line-by-line view of the whole process — instead of tracing relay logic by hand when something trips.

    Comex SCADA screen showing Line 1 and Line 2 process mimic diagrams, capacity gauges, dosing bin levels and a live event log at the RMU Kakanj Vrtlište plant
    Process mimic & event log Line 1 / Line 2 status, live capacity, all four dosing bin levels, wagon load readout, and a timestamped log of every start, stop, and local/remote control handover.
    Comex SCADA safety status screen for Line 1, showing green status indicators for each conveyor, screen, crusher and mill
    Line-level safety status Every conveyor, screen, picking table, crusher and mill reporting in real time, so a fault shows up as which machine, on which line, immediately.
    Chain conveyors
    Screen (sito)
    Picking table
    Main conveyors 1 & 2
    Crusher
    Reduction conveyor
    Mill
    4 × dosing bins
    Coal moving along the conveyor belt at the RMU Kakanj Vrtlište plant, viewed from the overhead gantry
    Results

    What changed on the ground

    • Full operational independence between Line 1 and Line 2 — no more cross-line cascading faults
    • Faster fault diagnosis via real-time SCADA visualization, replacing manual, cabinet-by-cabinet troubleshooting
    • Controlled VFD + soft-starter motor starting across every drive on site — lower mechanical stress, better motor and system protection, reduced energy use versus direct-on-line starting
    • Zero unplanned production stoppages during the changeover itself
    • A modernized platform on standard, supportable hardware, replacing equipment that had already run past its rated service life
    The project called for fully assembled electrical cabinets — pre-programmed and tested in advance — with the changeover carried out during non-operating hours, so production continuity was never disrupted.
    Almir Smajlović
    Head of Electrical Services, Pogon Vrtlište, RMU Kakanj
    This modernization has given us stable, reliable operation of the plant that receives, processes, and loads our coal. It's another example of our management staying aligned with modern technology in mining, and our strategic commitment to greater efficiency and safety.
    Edin Muminović
    Technical Manager, Pogon Vrtlište, RMU Kakanj
    At a Glance

    Project specification

    ClientRMU "Kakanj" d.o.o. — Pogon Vrtlište
    LocationKakanj, Federation of Bosnia & Herzegovina
    SectorCoal mining — receiving, processing & wagon loading
    ScopeFull control & power electrical replacement, new SCADA, 2 technological lines
    Delivered withSpark Industry d.o.o. Zenica; RMU Kakanj Electrical Services (Pogon Vrtlište)
    ControlSchneider Electric Modicon M241 PLC
    SafetySchneider Electric XPS-MC safety relay
    Motor controlSchneider Electric Altivar VFDs (per drive) + 1 soft-starter
    SupervisionDual-line SCADA / HMI — process mimic, live status, event log
    Cutover downtime0 minutes of production downtime — confined to non-working days
    Delivered in partnership with
    Comex d.o.o. Tešanj
    Control systems & automation
    Spark Industry d.o.o. Zenica
    Electrical works
    RMU Kakanj — Electrical Services
    Pogon Vrtlište
    On Site

    The plant, in operation

    Underside view of the elevated conveyor bridge structure against a clear blue skyConveyor carrying crushed coal past a safety light guard, with the Bosnia countryside in the backgroundA worker walking along the elevated conveyor gantry walkwayThe conveyor bridge supported on tall steel pylonsThe coal loading bunker with rail wagons positioned beneath it

    Running critical process equipment on control hardware past its service life?

    We plan modernizations around your production schedule, not the other way around — so the cutover itself never costs you uptime.